Dublin Port Crossberth Quay, RoRo Jetty and IED Environmental Dredging

GDG was commissioned by Roadbridge L&M Keating Joint Venture for the detailed design of a number of strategically important port infrastructure schemes in Dublin Port.

An image of a roll on roll off jetty

Crossberth Quay (CBQ)

Crossberth Quay (CBQ) is a new 170m long quay which was designed as a combi-wall structure tied back to a contiguous piled anchor wall. The quay is designed to accommodate some of the largest multi-purpose vessels and includes two bankseats to accommodate Roll On Roll Off (RoRo) vessels.

An image of a building site being converted into a quay

GDG were involved in developing and optimising the scheme solution which included geotechnical interpretation of the soil parameters, developing the construction methodology and sequence and detailed design of all the structural members in the CBQ. A suite of 2-D and 3-D finite element analysis were undertaken to optimise the design.

GDG were also the appointed Project Supervisor Design Process (PSDP) involving managing the design HS&E risks for the project.

GDG’s responsibilities included:

  • Scheme Design development and optimisation for Cross Berth Quay
  • Geotechnical Interpretive reporting
  • Detailed design of Quay wall, Anchor wall, Tie rods & fittings, Waler Beam, Cope Beam, Bankseat Piling & RC Details.
  • Drainage Layout
  • Fixtures and Fittings
  • End Return Wall
  • Pavement Slab and Concrete Works
  • Temporary Works
  • Detailed drawings
  • Project Supervisor Design Process (PSDP)
  • Construction Support
  • Safety File
  • Contract Administration

RoRo Jetty

GDG in partnership with Arch Henderson, were commissioned for the detailed design of the Dublin Port RoRo Jetty. The 250m long jetty structure comprises 9 separate dolphins that allow berthing on either side of the structure. Walkways adjoin each dolphin and also to the adjacent CBQ site within Alexandra Basin.

An image of a roll on roll off jetty

GDG was responsible for the design of all of the piles used to support the jetty structure. This process involved geotechnical interpretation, analysis and technical reporting in conjunction with considering the various load regimes imposed on the structure as a result of simultaneous berthing and mooring, which varies between specific dolphins. Geotechnical design also included for the specific choice of toe levels above bedrock in order to reduce pile installation timescales and associated risks of working with marine based plant and equipment.

As part of the design GDG also assessed the relative increase on lateral moments as a result of dredging, due to the effective lowering of the seabed as part of planned capital and follow-on maintenance dredging works in Alexandra Basin.

GDG’s duties under this project included:

  • Collaborative working with marine structural designer and Design & Build Contractor
  • Geotechnical interpretation, analysis and reporting
  • Detailed geotechnical design of all piles supporting the jetty structure, e.g. 86nr piles approximately ranging between 32m – 39m long
  • Detailed Design of linkspan guide piles
  • Mitigating pile installation risks by specifically designing pile toe levels above suspected rockhead levels
  • Project Supervisor Design Process (PSDP)

Industrial Emissions Directive (IED) Environmental Dredging

GDG was commissioned to review the nature of the material arising from dredging works in Alexandra Basin and to make recommendations relating to how the material could be treating and stabilised. In the interests of the end user client, Dublin Port, it was imperative for treatment of the material to facilitate on-site re-use wherever possible and to minimise the amount of off-site disposal in order to reduce the overall construction cost of the project. The dredged material is to be infilled with the stabilised dredge material at an existing Graving Dock (GD2) which is located adjacent to Berth 28 within the port.

Using the recommendations given by GDG, the RBLMK JV was appointed as the preferred Contractor to deliver the project. GDG was awarded the detailed design relating to the design of the proposed stabilisation mix and development of the material re-use strategy to be implemented by the Contractor on site during the proposed works. With this role GDG liaised with all necessary statutory authorities in order to ensure that the material is compliant from both geotechnical and environmental perspectives, particularly in terms of meeting necessary requirements from bodies such as the EPA.

An image of a dredging project

GDG implemented their detailed design on site during the works in terms of ensuring stringent but appropriate QA / QC compliance procedures were in place from the Contractor and their Subcontractors. This involved preparation of detailed specification and review of all Contractor Method Statements during the works.

GDG’s responsibilities included:

  • Environmental Dredge Design
  • Stabilisation Mix Design
  • Bund Design incl Slope Stability
  • Compliance with Statutory Licensing Requirements
  • Contract Specification
  • Review of Contractor’s Proposals
  • Technical Reporting
  • Site QA / QC Compliance Checking

Latest

You might also be interested in

All articles
Ports & Harbours
An image of a large boat in Greenock ocean terminal

Greenock Ocean Terminal

GDG was commissioned by Roadbridge for the detailed design of the new cruise liner berth at Greenock Ocean Terminal.

Find out more
Ports & Harbours
An image of a wharf extension

Dinish Wharf Extension

GDG was awarded the detailed design services contract relating to Castletownbere Fishery Harbour Centre, Dinish Island, Co. Cork.

Find out more

Get in touch.

Do you have a project to discuss? Get in touch with us today.